Dear Team,
Would like to know what exactly happens in the "Migrate Hosts" steps in Distributed Firewall, Hosts, and Workload NSXV to T Migration option, could someone please throw more light on the same.
Thank you in advance...
In the "Migrate Hosts" step the nsx-v vibs will be removed from the hosts and the nsx-t vibs will be installed.
Depending on the maintenance mode (automatoc or manual) choice VMs will be migrated automatically off the hosts and put into maintenance mode before the nsx-t vibs will be installed. You can also specify to migrate hosts in serial or parallel order in the clusters.
In the "Migrate Hosts" step the nsx-v vibs will be removed from the hosts and the nsx-t vibs will be installed.
Depending on the maintenance mode (automatoc or manual) choice VMs will be migrated automatically off the hosts and put into maintenance mode before the nsx-t vibs will be installed. You can also specify to migrate hosts in serial or parallel order in the clusters.